Just over 400 large data centers used as much electricity in a single year as the entire state of Michigan. The findings highlight the heavy power demands of the nation's largest computing facilities as federal agencies consider tracking their energy use,.

The research, published in *Nature Sustainability*, was conducted by a Harvard-led team. Because federal and state governments do not track data center energy use separately from the rest of the power grid, researchers had to build their own list of facilities. They combined industry data with satellite imagery to identify 403 operational facilities between May 2024 and April 2025.

The study focuses exclusively on hyperscale data centers, which are the largest facilities run primarily by cloud and artificial intelligence operators. While these sites are often associated with artificial intelligence, not all of the surveyed facilities are used for that purpose.

"Hyperscalers have been growing fast, even before the AI boom," energy researcher Jon Koomey, who was not involved in the study, said.

The researchers estimate that the combined electricity usage of these 403 facilities landed between 68 and 99 terawatt-hours, with a middle estimate of about 82 terawatt-hours. That middle figure accounts for roughly 1.8 percent of all electricity consumption in the United States.

The geographic distribution of this power draw is heavily concentrated. Virginia's 142 facilities account for roughly a quarter of the total energy use in the study. When combined with Oregon, Ohio, and Iowa, those four states account for about half of the total power consumption recorded.

The environmental impact varies widely depending on the local power grid. Facilities in Oregon draw on relatively clean energy, while those in Virginia, Ohio, and Iowa rely much more heavily on fossil fuels. Across all surveyed locations, more than half of the electricity came from natural gas and coal, causing emissions to more than triple compared to estimates from before the artificial intelligence boom.

The actual energy totals are likely higher because the study did not account for electricity generated by on-site power plants or facilities that opened after April 2025. Developers increasingly build their own power generators when faced with long wait times for grid connections.

Furthermore, the facilities analyzed in the study are smaller than what is currently being planned. The average facility size in the dataset was 40 megawatts, whereas developers are now proposing campuses measuring hundreds or thousands of megawatts. Gianluca Guidi, lead author of the study and a postdoctoral research fellow at Harvard's T. H. Chan School of Public Health, told *Wired* that some of the massive campuses being proposed today are "substantially larger than the typical facility" his team looked at.

Federal tracking of these energy demands could soon expand. The Energy Information Administration conducted pilot surveys of data center power use across 10 states and is using the results to design a potential voluntary survey for the sector.

Summary

  • A small group of 403 large data centers consumes as much electricity annually as an entire U.S. state.
  • More than half of the electricity used by these facilities comes from fossil fuels, driving emissions well past pre-AI projections.
  • Future power consumption could outpace current estimates as developers build larger campuses and increasingly rely on private, on-site power plants,.